260 Pioneer Road, Spruce Grove, AB · CSTN 2370 · Simulation & Estimate Model (Structure Design per S2 / Protostatix Permit Drawings)
| Item / Rate | Rate Used | Source Document |
|---|---|---|
| Piling Crew Labour Foreman / Drill Op / Loader Op / Lab |
$76.00 / $70.50 / $40.60 / $26.50 /hr |
Initial Instr. §1a Unburdened hourly rates |
| Piling Productivity Shaft + 60° Bell (2 rigs) |
0.0284 crew-hr/ft + 3.0 / 3.375 / 3.75 hr |
Initial Instr. §1 & Memo #1 R2 |
| Rebar Cages & Dowels Tied cages + 20M/15M dowels |
$450/pile cage; $2.50/kg (assumed) |
Memo #1 R2 & S1.02 Note 15 |
| Geotech & Tailings Continuous insp. + export |
$138.00/hr insp.; $6.55/Lm³ export |
Initial Instr. §1, §1b Subcontract items |
| Div 3 Blended Crews Formwork Carp / Concrete Place |
$42.56/hr carp; $38.75/hr placing |
Memo #2 (2026) Unburdened blended rates |
| Ready-Mix Concrete S-2 / N / C-1 + Winter Heat |
$275 / $265 / $285/m³; +$45/m³ Nov 1–Apr 30 |
Initial Instr. §8 & S1.02 Schedule |
| Concrete Pumping 38m, 42m, 47m, 52m booms |
$190–$350/hr + $4–$6/m³ +$9.50/hr CO₂ + 14% sur. |
Noremac 2023 Quote & Memo #2 §9a ($250/m³ waste) |
| Flatwork Place & Finish SOG & Suspended Slabs |
$23.50/m³ SOG; $19.78/m³ Susp. |
Odie's Concrete Quote (Sep 2 — sub-trade) |
| Formwork Materials Ply, 2×4, collars, joists, tables |
$68.50/$67 ply; $325/MBF; $35/mo collar; $135/mo truss |
Initial Instr. §2, Memo #2, #3, #4 |
| Rebar S/I, Burden & TC Memo #3 Scope Additions |
$2,890,750 rebar LS; 55% burden; $28,700/mo TC |
Memo #3 (2026) Added below sub-totals |
| Access & Rig Matting 80 road mats + 39 rig mats |
$1.75/day road mat; $15.00/day rig mat |
TerraPro Q8694 & Site Matting Brief |
| Equipment & Spec | Qty / Duration | Rate & Fuel/Maint |
|---|---|---|
| 2× Soilmec SR-55 Drill Rigs Ø500/Ø600 shafts + 60° bells |
837.89 rig-hrs (42 prod days) |
$275.00/hr · 250 L/rig/day Maint: 12% mach-hr ($350/hr) |
| Rig Lowbed Trucking 2 rigs × mob in + demob out |
4 one-way moves | $3,500.00 / move ($14,000 total) |
| Articulated Wheel Loader 2–3 LCU bucket (replaces 2 SSL) |
460 hrs (46 days incl. mobe) |
$165.00/hr (AHRCA est.) 85 L/day · Maint: 6% |
| Piling Crew Truck Full piling duration |
46 working days | $85.00/day · 100 L/week Maint: 4% mach-hr |
| Piling Hand Tools & Tremie Vibrators, drop chute, hoppers |
42 prod days | $65.00 / day ($2,730 total) |
| Tower Crane + Placing Bucket 56m jib, 25-person crew cap |
~8 mos (Oct 27– Jun 30, 2027) |
$28,700/mo (Memo #3) Bucket: 50–70 m³/hr |
| Noremac Boom Pumps 38m (13×), 42m (14×), 47m (4×), 52m (4×) |
35 callouts (159.15 pump hrs) |
$210–$350/hr + $5/m³ avg +$9.50/hr CO₂ + 14% sur. |
| Structure Small Tools Vibrators, concrete bucket allow. |
180 working days | $120.00 / day ($21,600 total) |
| TerraPro Site Matting 80× 8'×14' 3-ply + 39× 8'×20' rig |
240 rental days + install/trucking |
$174k rent + $21.3k ops ($195,330 + tax) |
| BOXX Site Trailers (Ref.) 12×40 office, 12×60 lunch, 12×32 lav |
Example Q-69087 (confirm duration) |
$5,378/mo equipped +$7,805 transp./clean |
| Scope | Labour | Mat/Eq/Sub | Total |
|---|---|---|---|
| Drilled CIP Piles (184) | $134,570 | $809,019 | $943,589 |
| Div 3 Structure (Base) | $298,617 | $1,873,890 | $2,172,507 |
| Base Direct Subtotal | $433,187 | $2,682,909 | $3,116,096 |
| Item | Calculation | Amount |
|---|---|---|
| Rebar Supply & Install | Memo #3 Lump Sum | $2,890,750 |
| Labour Burden (55%) | 55% × $433,187.36 | $238,253 |
| Tower Crane (~8 mos) | 8 mos × $28,700/mo | $229,600 |
| TerraPro Site Matting | Quote Q8694 | $195,330 |
| Combined w/ Memo #3 | Incl. Rebar/TC/Burden | $6,670,029 |
| Pile Casing (25% / 50%) | 633.3m / 1,266.5m | $69,659 / $139,318 |
| Pile Casing (80% / 100%) | 2,026.4m / 2,533.1m | $222,908 / $278,636 |